Installer & contractor support
Practical DNO application and grid connection support for installers, developers and electrical contractors across Great Britain.
Best suited to commercial and light industrial schemes where export capacity, reinforcement, G100 export limitation or DNO technical queries could affect cost or programme.
Currently accepting installer and contractor enquiries for Q2/Q3 2026
• G98/G99 application support
• Commercial solar DNO applications
• Single line diagram review
• Import/export capacity advice
• G100 export limitation advice
• EV charger DNO application support
• Heat pump and electrification load review
• DNO offer and query support
Pricing
Commercial G99 application support from £450 + VAT. Complex or multi-technology sites — including co-located solar and BESS, or sites with export limitation requirements — are quoted on scope.
Get in touch with a short project overview and you’ll get a clear fee within one business day.
Some projects are not complicated enough to justify a large consultancy team, but are too important to treat as a form-filling exercise.
That is usually where DNO capacity, export limits, reinforcement costs, equipment assumptions or technical queries start affecting customer price, programme or feasibility.
Typical support ranges from commercial-scale schemes through to multi-MW distribution-connected projects.
Commercial schemes
Most G99 support services are built around high-volume domestic installs. Commercial and light industrial schemes — typically 50kW to 1MW — involve a different level of complexity: export limitation strategy, multi-technology arrangements, reinforcement risk, and DNO technical queries that require more than form-filling to resolve.
This support is aimed at installers and contractors who need someone who understands the network, not just the paperwork. If the DNO comes back with a position you’re not comfortable with, or the connection arrangement is affecting your commercial offer to the end customer, that’s where this service adds most value.
Generally applies to fully type-tested microgeneration up to and including 16A per phase.
Approximate limits: 3.68kW single-phase or 11.04kW three-phase.
Applies where generation or storage exceeds 16A per phase, or where the installation falls outside G98 requirements.
Usually requires DNO assessment and approval before commissioning.
Relevant where installed capacity is greater than the agreed export limit and export limitation is used to stay within the DNO-approved export capacity.
Common on commercial solar PV, BESS and constrained sites.
The exact route depends on project size, voltage level, DNO and site arrangement, but most installer-led commercial projects follow a version of this process.
G98 single premises
Often a connect-and-notify route where the DNO is notified after installation, provided all G98 conditions are met.
G99 LV projects
Often planned around a DNO response period of around 45 working days once a complete application has been submitted.
Larger / HV projects
Can be closer to 65 working days or longer, particularly where reinforcement, interactivity, constraints or commercial terms are involved.
Timescales vary by DNO, completeness of information, voltage level, project complexity and network conditions.
This is not a high-volume admin service. The support is aimed at installers and smaller developers who need senior grid input when a project becomes technically or commercially awkward.
The value is in spotting issues early, giving installers clearer DNO-facing information, and helping avoid avoidable delays, poor assumptions or weak customer commitments.
A G99 application is the formal DNO process used where generation or storage equipment connects in parallel with the distribution network and falls outside G98 limits. In practice, this usually means systems above 16A per phase, or projects that need a more detailed DNO assessment before installation or commissioning.
G98 generally applies to fully type-tested microgeneration up to and including 16A per phase — approximately 3.68kW on single-phase or 11.04kW on three-phase at nominal voltage. G99 applies above that threshold, or where the installation does not meet the relevant G98 conditions.
At nominal voltage, 16A per phase corresponds to approximately 3.68kW on a single-phase supply and 11.04kW on a three-phase supply. Anything above those limits should normally be considered under G99, although the correct route still depends on the full site arrangement and equipment details.
For many lower-voltage projects, DNO assessment is often planned around a 45 working day response period once the application is complete. Higher-voltage or more complex connections can be longer, commonly around 65 working days or more depending on scope, reinforcement, interactive queue position and DNO requirements.
If the project requires G99 approval, it should not normally be commissioned in parallel with the network until the DNO has approved the connection arrangement. Starting too early can create compliance, programme and commercial issues if the DNO later requires export limitation, reinforcement or a different connection arrangement.
Typical inputs include site address, MPAN, proposed generation/storage capacity, inverter details, single line diagram, import/export assumptions, protection information, equipment certificates and any export limitation arrangement. Missing or inconsistent information is a common cause of delay.
G100 export limitation is used where installed generation or storage capacity is higher than the agreed export limit. It is common on commercial solar PV and battery projects where the site wants a larger installed system but the DNO will only allow a lower maximum export level.
EV chargers are demand/load, so they do not normally require G99 by themselves. They may require DNO notification or approval under EV/heat pump connection processes. If EV charging is combined with solar PV, battery storage or export-capable generation, G99 and/or G100 may become relevant.
The most common causes are incomplete or inconsistent technical information — missing inverter certificates, incorrect MPAN, mismatched single line diagrams, or export assumptions that don’t align with the proposed equipment.
On more complex sites, failure to identify export limitation requirements early, or submitting without understanding the DNO’s local network constraints, can result in significant delays or unexpected reinforcement costs. Getting the application right first time is almost always faster and cheaper than correcting a rejected submission.
Speak before pricing the job, agreeing programme dates, promising export capacity, ordering major equipment or accepting a DNO position you are not comfortable with. Grid issues are usually easier to deal with before the commercial offer to the customer is locked down.
Send a short overview of the project, site location, proposed capacity and the decision you are trying to make.
Response typically within 1 business day.